Increasing Venetia Mine’s ROM production

Installation of double deck Omni Screens at Venetia Mine to enable the feed from the crushers to be separated into coarse and fine streams.

Installation of the dewatering screen below the new wet crusher.

Extension to existing transfer house.


New conveyor installed at Venetia to bypass the scrubbers.


BATEMAN has modified sections of the existing plant at the Venetia Mine 80 km west of Messina, RSA, to increase the throughput of run-of-mine (ROM) ore from 4,5M to 5,9M t/yr.

The project arose out of an in-house study by Venetia that revealed the feasibility of increasing the plant throughput, providing appropriate modifications were made. The mine’s process engineers developed the conceptual flow sheet.

BATEMAN prepared a technical and cost-estimate proposal to implement the modifications and was awarded a R10,8M reimbursable contract on condition that several requirements could be met. As much as possible of the existing installation would have to be re-used and the existing plant’s high standard of access and maintenance would have to be maintained. There would have to be minimal impact on current mine production and BATEMAN’s involvement in the project would have to be completed within five months, with hot commissioning commencing early in March 2003.

Safety was to be a critical and high- priority factor at all stages of construction and commissioning, particularly as the modifications were to be executed in an operating plant with a very good safety record.

The project involved exchanging the existing secondary crusher’s dewatering screens and associated underpans and chutes with double-deck screens, to enable the feed from the crushers to be separated into coarse and fine streams. In addition a dewatering screen was introduced below the new re-crush crusher which discharges onto a modified conveyor. The fine-material stream now bypasses the secondary scrubbers, effectively providing additional capacity.

So the fine material could be sent to the discharge hoppers of the scrubbers, an existing conveyor was extended and re-aligned with the drive being repositioned in the refurbished building. A new conveyor was installed and the scrubber building modified extensively.

The project was completed on time and as per the client’s specifications. The BATEMAN project team also maintained an exemplary safety record and during the 9 664 man hours worked on site, no lost-time accidents were incurred.

More information may be obtained from James Nieuwenhuys, General Manager, Diamonds on +27-11-899-2262 or email jamesn@bmi.co.za.

VIEW PDF